The Federal Government has approved the commencement of procurement for the proposed East and West Super Grids as part of efforts to strengthen Nigeria’s national electricity network and increase transmission capacity from about 5,000 megawatts (MW) to 19,000MW within two years.
The Minister of Power, Joseph Olasunkanmi Tegbe, disclosed this on Wednesday, October 28, 2026, while briefing State House correspondents on the outcome of the Federal Executive Council (FEC) meeting presided over by President Bola Tinubu at the Presidential Villa, Abuja.
According to the minister, the proposed projects are designed to improve grid resilience, reduce transmission bottlenecks and enable the country to evacuate more electricity from generation plants to consumers.
Tegbe explained that the East and West Super Grids would cut across the northern and southern parts of Nigeria rather than serve specific geographical regions.
He said the projects would strengthen the country’s electricity transmission backbone, with improved connections extending from Sokoto through Abuja and other locations into parts of southern Nigeria.
The minister noted that Nigeria currently has more than 13,000MW of available electricity generation capacity, but the existing transmission network can reliably transmit only about 5,000MW.
He said the proposed expansion would help address the gap between electricity generation and transmission, allowing more available power to reach homes, businesses and industries.
Beyond the Super Grid initiative, the Federal Executive Council also approved three additional interventions aimed at strengthening transmission infrastructure around Abuja and Lagos.
The first involves the construction of a 33-kilovolt double-circuit underground and overhead line connected to the Katampe Transmission Substation in Abuja.
The second covers the design, manufacture and supply of three 300MVA, 330/132/33kV transformers for the Ikeja West Transmission Substation in Lagos.
The third involves the reconstruction and upgrade of the 35.6-kilometre Itumola–Mapasin–Sagamu 132kV transmission line from a single-circuit to a double-circuit line to accommodate increasing electricity demand along the Lagos-Sagamu corridor.
Tegbe said the interventions form part of a broader strategy to improve electricity transmission, stabilise the national grid and maximise existing power sector infrastructure.
The minister also disclosed that the government had commenced a nationwide technical audit of electricity infrastructure to identify ageing and weak facilities requiring replacement or rehabilitation.
The audit covers three major energy zones: Lagos and its surrounding industrial corridor, the Abuja-Kaduna-Kano axis, and the Enugu-Onitsha-Benin axis.
On the financial challenges affecting the electricity sector, Tegbe said the Federal Government had paid N1.23 trillion out of the N3.3 trillion owed to gas suppliers and other stakeholders in the power industry.
He explained that outstanding liabilities had contributed to difficulties in securing adequate gas supplies for electricity generation companies.
The government is also working to improve the operational efficiency of the Transmission Company of Nigeria and the Nigerian Independent System Operator to strengthen coordination in grid management and infrastructure development.
Despite the ambitious 19,000MW target, the success of the proposed Super Grids will depend on effective procurement, financing, timely construction and improvements across the entire electricity value chain.
The expansion of transmission capacity alone will not guarantee uninterrupted electricity supply unless generation and distribution infrastructure are strengthened alongside it.
The Federal Government says the proposed projects are intended to address longstanding infrastructure limitations and improve the country’s ability to deliver available electricity to consumers nationwide.